Sebeș-Turda highway underpass, feeding Alba county!

A memorable work, by which Valrom demonstrated his ability to leader on the market, through creativity, innovation, professionalism and quality!

Under the coordination of the Commercial Director at that time, the design and execution of the work was carried out. The team consisted of the welders, the sales agent and the area manager, who ensured that the project met the deadlines set in the schedule, as well as overseeing the execution steps.

The construction file executed by Valrom was handed over to CNAIR and ALBA Water Authority.

Location: Alba county
Completion year: 2015
Project title: Undercrossing the Sebes-Turda highway, feeding Alba county
Products: WaterKIT – Cold water supply system, GasKIT – Gas supply system

a. D800 sockets;

b. PEHD water pipe PN10 D800 taking over OL D1000 pipe & PEHD water pipe PN 16 D800 taking over OL D1200 pipe;

e. D800 thermoformed curves;

f. mounting compensators and valves, breathers, drain kits (all mountings with dynamometric adjustment keys).

g. draining and hydraulic venting chambers.

The hollow and hydraulic vent chimneys were specially designed by Valrom Industrie.

mounting it was made in the canal, and the pipe was launched on mental rollers, under the highway.

Types of welding used:

a. head to head;

b. electrofitting.